• news-banner

    Expert Insights

Essential law: Variations - Part one

In the first of a series on the basics of construction law, James Worthington and Vanessa Jones begin with variations, considering here the scope of the right to instruct variations.

The variations regime is fundamental to both parties to a construction contract. It gives the employer the flexibility to change the works, and determines the extent to which the contractor will be allowed additional time and money for such changes.

This article will look at some of the issues regarding the extent of the employer’s right to instruct a variation and the contractor’s right to claim that an employer’s instruction is a variation.

What is a variation?

Most construction contracts will include a definition of what is a “variation” under that contract. In general terms, a variation is an instruction by the employer to alter the works to be performed or an instruction to vary their timing, method or sequence.

However, not all instructions will be treated as variations. In particular:

  • Where the instructed work is “indispensably necessary” to complete the contract works, the court will generally infer that it is included in the contracted works, regardless of the fact that it is not expressly identified in the specification. 
  • Where the contractor has agreed to design and build a facility to meet certain performance specifications, changes to the design required to meet those performance specifications will generally not be a variation.
  • Where the contractor has taken on a risk under the contract (such as ground conditions), any delay or additional cost that arises from that risk will be the responsibility of the contractor, and will generally not be a variation even though the methodology required to complete the works may have changed.
  • Where the contract gives the architect the power to determine the method by which the works are executed, it is generally not a variation if the architect chooses a specific methodology, even if that choice was unreasonable.

Can an employer instruct any variation?

There are certain limits on the employer’s right to instruct a variation that will generally be implied into a construction contract, such that the following are not permitted (unless expressly permitted by the contract or agreed by the contractor):

  • Instructions that fundamentally change the nature of the contract, or were clearly not contemplated by the original contract. The guiding principle is that after such variation the works should still be capable of being identified as the works originally defined in the contract.
  • Instructions that omit works for the purpose of awarding those works to another contractor. If an employer intends to omit work, it should be for the purpose of omitting that work entirely from the project. The courts have held that a contractor has both an obligation to do the works, and a corresponding right to be able to do those works.
  • Instructions after practical completion has already occurred. 

Does the contractor have the right to carry out additional work? 

A contract may give the employer the right to instruct additional work, but that does not mean there will be an implied term that if additional work is required, the employer must instruct the contractor to carry it out.

Can the contractor object to a variation?

This would depend on the terms of the relevant variation clause. However, the standard forms generally contain a limited right for the contractor to object. For example, JCT provides that a contractor may make a reasonable objection to an instruction that relates to the imposition by the employer of any restrictions regarding access, limitations of working space or working hours or the execution of work in a specific order.

Are there circumstances where an employer is obliged to instruct a variation?

Certain standard form contracts (such as the old ICE conditions) place a positive obligation on the engineer to instruct a variation if this was necessary for completion. However, whether such an obligation may be implied is more complex. There is a tension between the contractor’s obligation to build what is described in the contract even if that is impossible, and the implied duty on the employer to co-operate.

What if there is no variation clause?

All standard form construction contracts contain variation clauses, but what if the parties have contracted on, say, a simple agreement of price and scope of work without a variations clause?

First, there is no implied right for an employer to instruct a variation under a construction contract. Therefore if there is no express contractual right for an employer to instruct variations, the contractor can refuse to carry out such variations without consequence.

Second, if the contractor agrees to carry out such variation, this varied work may be construed as a new contract such that the varied work is valued on a different basis than under the original contract and not based on the rates and prices in that original contract.

This article was written by James Worthington and Vanessa Jones at Charles Russell Speechlys and was first published in ‘Building’ magazine on 5 March 2020.

Our thinking

  • Building Safety and the challenges for UK construction - where are we now?

    David Savage

    Events

  • Women in Leadership: Resilience in Entrepreneurship

    Events

  • Dominic Lawrance and Catrin Harrison write for Tax Journal on the implications of the Court of Appeal judgment in the case of ‘A Taxpayer v HMRC’

    Dominic Lawrance

    In the Press

  • The Telegraph quotes Sarah Jane Boon on Labour’s plans for cohabitation reform

    Sarah Jane Boon

    In the Press

  • Something Changed – Landlord recovers possession of iconic music venue

    Samuel Lear

    Quick Reads

  • Implications of Johnson v FirstRand – will secret commissions pave the way for claims from Auto ABS noteholders?

    Caroline Greenwell

    Insights

  • When is 20% not 20%? The real impact of the proposed changes to business property relief on trading companies

    Sarah Wray

    Quick Reads

  • Joseph Evans, Cassidy Fan and Jessica Boxford write for New Law Journal on the future of insolvency: a digital asset revolution

    Joseph Evans

    In the Press

  • Cohabitation law reform

    Hannah Owen

    Quick Reads

  • Property Patter - Lifetime achievements: Katie Kopec of JLL

    Emma Humphreys

    Podcasts

  • Charles Russell Speechlys finds that Gen Z prioritises financial planning and saving amidst growing economic challenges

    Sally Ashford

    News

  • Law 360 quotes Stewart Hey on the potential integration of the PSR into the FCA and the impact on APP fraud reimbursement

    Stewart Hey

    In the Press

  • Kevin Gibbs and Sadie Pitman write for CoStar on the need for investment in power infrastructure to support new data centres

    Kevin Gibbs

    In the Press

  • New code of practice for the cyber security of AI development

    Rebecca Steer

    Quick Reads

  • Drapers quotes Kerry Stares on the potential for a review of the Modern Slavery Act 2015

    Kerry Stares

    In the Press

  • EU Design Legislation Updates

    Matthew Clark

    Insights

  • The EU Omnibus: resetting the rules on sustainability due diligence

    Kerry Stares

    Insights

  • The Times and Daily Mail quote Dan Pollard on new changes to the Employment Rights Bill

    Dan Pollard

    In the Press

  • Extra Time: The business of women’s football in Africa

    Sarah Johnson

    Podcasts

  • Singaporean Court Declines to Revisit SIAC Registrar’s Administrative Decision

    Thomas R. Snider

    Insights

Back to top